Aurora Apartments
CLIENT: Bovis Lend Lease
CLIENT REP: Jim Neville
CONTACT NO: (07) 3225 7100
ENGINEER: ARUP
GEO-TECH: Golder Associates
VALUE: $450,000
DURATION: May 2003 – August 2003
grey-line

These works included site clearing, bulk excavation and removal of 35,000m3 shale rock and detailed excavation. Works were carried out in conjunction with the shoring operation, works were carefully planned and programmed so as to ensure timely and safe completion.  The excavation was up to 14m deep and included a 4.5m deep lift pit in the middle of the site.  In order to ensure stability, the perimeter of the excavation was pre drilled thus providing a stable work face, on completion of the excavation rock spall mesh was placed on the face of the excavation for the safety of workers. 

Traffic control was paramount for the exiting of trucks onto busy Queen St, this was completed without incident.  Our contract also included a stormwater diversion approx 45m in length which was completed out of hours to the satisfaction of the Brisbane City Council.

aurora-pics
            
            
greyline-770



            
coles
SHAMROCK TEAM:

Anthony Hallagan
Estimator

Anthony Hallagan
Project Manager

Jim Steward
Site Supervisor



            
Garden City - Coles Relocation
CLIENT:   JOHN HOLLAND
CLIENT REP:  Allan Brown
CONTACT NO: (07) 3368 3144
ENGINEER:  MPN (Greg Tyquin)
VALUE:  $1,000,000
DURATION:  Dec 2002 – Nov 2003


grey-line
Shamrock Civil were awarded the civil component of the Coles Relocation at the busy Garden City Shopping Centre by John Hollands, this project was staged so as to minimize disruption to trading. Stage 1 included demolition of existing carpark, bulk excavation and detailed excavtion including cutting down approx 300 piles. Stage 2 included stormwater and approx 15,000m2 of pavements.

Works were completed in accordance with John Hollands various critical handover dates.

coles-pics
            
greyline-770



            
ipswich
SHAMROCK TEAM:

Brendan Kealy
Estimator

Brendan Kealy
Project Manager

John Esler
Site Supervisor



            
Ipswich Recreation Centre - Collingwood Park
CLIENT:   Walter Construction
CLIENT REP:  Eddie Gangemi
ENGINEER:  GHD – Andrew Winters
VALUE:  $220,000
DURATION:  December 2002 – June 2003
grey-line
Shamrock Civil were awarded the contract for the decontamination & civil works at the new Ipswich Recreation Centre at Collingwood Park. The site was formally used as a firing range which resulted in high levels of lead, specialists were appointed to verify for unexploded ordinates.
An extensive E&SC management plan was implemented to ensure minimal run off from the site, these included cut off drains and a detention basin.

We utilized a grid system for the systematic removal of contaminated soil; each grid was verified on completion of excavation by GHD, all material removed were placed in stockpile and covered with previously stripped topsoil.
Following verification of the decontamination we undertook bulk earthworks and approx 5,000m2 of asphalt pavements.

ipswich-pics
            
greyline-770
            
northlakes
SHAMROCK TEAM

Andrew Kerr
Estimator/Project Manager

Paddy O’Boyle
Site Supervisor

Carl Eaton
Site Supervisor/QA coordination
            
Northlakes shopping Centre
CLIENT:   Westfield Design & Construction
CLIENT REP:  Andrew Cosgrave
CONTACT NO: (07) 3878 9300
ENGINEER:  MPN Greg Tyquin (07 3371 8877)
VALUE:  $ 2,200,000
DURATION:  November 2002 – July 2003

grey-line
This contract included earthworks, storm water and electrical conduit installation.  The major component of our works is included construction of approx 40,000m2 of flexible pavements, for the new Westfields Northlakes Shopping Centre.  Pavements included heavy duty access roads, loading docks & intersections and light duty car park areas.  Contract also included line marking and road furniture.  Prior to completion we undertook the hard landscaping to the perimeter of the site.  All works were completed in accordance with Pine Rivers Shire Council standards and MPN specifications.  On completion of the project a Quality Manual was compiled, this included signed QV forms for the various components and stages as well as test certificates and as-constructed drawings.
northlakes-pics
            