Large enough to get things done
               – small enough to get it done right
            
Our projects in 2005
greyline-770

 
            
ststephens
SHAMROCK TEAM

Antony Hallagan
Estimator

Carl Eaton / Eamonn Turner
Site Supervisors

Antony Hallagan
Project Manager

            
St Stephens Cathedral Development
CLIENT:  John Holland Contractors
CLIENT REP:  David Marshall
CONTACT NO: 0414 321483
ENGINEER:  Butler Partners (Mike Neighbour)
VALUE:  $500,000
DURATION:  March 2004 – January 2005
grey-line
Our contract included demolition of in ground structures, bulk excavation, underpinning, detailed excavation & backfilling. Due to the confined nature of the site and limited access, the works were carefully programmed to cause minimal disruption to church services and access to Charlotte St.

Approx 6,000m3 of rock was excavated and removed from site, excavations were staged so as to allow the shoring system an underpinning works to progress in accordance with program.
ststephens-pics
            
greyline-770



            
macktruck
SHAMROCK TEAM:

Andrew Kerr
Estimator

Gareth Rhodes
Project Manager

John Esler
Site Supervisor

            
Mack Trucks, Richlands
CLIENT:  PPK           
CLIENT REP:  Greg Tyquin
CONTACT NO:  (07) 3371 6677
ENGINEER:  MPN
VALUE:  $750,000
DURATION:  October 2004 – March 2005 

grey-line
Shamrock Civil were awarded the contract for the construction of a new Industrial Park at Richlands, the scope of works included site decontamination earthworks, services and pavements.

Decontamination works involved removal and disposal of asbestos contaminated soils in accordance the requirements of the EPA. This was followed by site earthworks including aprox 10,000m3 cut to fill to form road subgrade, building platforms and detention basins.

Service installations included stormwater, water, sewer, telecom and electrical reticulations.
The project was finished off with hard landscaping, footpaths and an asphalt paved road.

macktruck-pics
            
greyline-770


            
woolworths 1

SHAMROCK TEAM

Andrew Kerr
Estimator

Derek Hennessy
Site Supervisor

Callan Stephens
Project Manager


 

            
Woolworths, Tewantin
CLIENT:   W.A. Stockwell Pty Ltd
CLIENT REP:  Shane Percy
CONTACT NO:  (07) 3033 9320   
VALUE:  $885,000
DURATION:  April 2005 – November 2005
grey-line
The early works civil package for Tewantin consisted of bulk earthworks, bored piers with earth retention anchors and shotcrete to retain the perimeter of the excavation.  A reinforced concrete capping beam was poured on top of the bored piers to lock in the retention system. Sewer & stormwater works within and external to the site were performed.

The project required detailed planning and programming to ensure the coordination of all works. Silt management was managed to comply with Noosa Shire Council’s requirements.

The project was completed on time and within the client’s budgetary constraints.
woolworths 2
            
greyline-770

 

 

            
coomera 1
SHAMROCK TEAM

Andrew Kerr
Estimator

Gary Grace
Site Supervisor

Callan Stephens
Project Manager

            
Coomera Tavern
CLIENT:   Construction Engineering
CLIENT REP:  Bradley Blanck
CONTACT NO:  (07) 5591 5491
VALUE:  $914,000
DURATION:  August 2004 - March 2005
grey-line
Shamrock Civil Engineering was appointed by Construction Engineering to do the following at the Coomera Tavern site:
 
·   Cut & fill over a site of approximately 16000m˛
·   Drain & construct a new retention basin
·   Construct 2 pads for the Tavern & Restaurant  and Bottle Shop
·   Construct car par for 400 cars
·   Rebuild new road, kerb & culvert
 
All works were completed on time and to a high quality which met Construction Engineering’s standards.
coomera 2
            
greyline-770

 

 

            
rickerttrd 1
SHAMROCK TEAM:

Antony Hallagan
Estimator

John Esler
Site Supervisor

Antony Hallagan
Project Manager

            
Rickertt Road Widening
CLIENT:   Brisbane City / Redland Shire Councils
CLIENT REP:  Peter Young
CONTACT NO:  (07) 3710 1128
VALUE:  $530,000
DURATION:  May 2005 - November 2005
grey-line
Shamrock were engaged by Redland Shire council to widen approximately 400 metres of Rickertt Road. Rickertt Road is a major council road with high traffic volumes.
 
Works consisted of earthworks, pavements, kerbing and footpaths.
 
The project required detailed planning to ensure safety and traffic flow, whilst construction took place. All the works were completed to a high specification & kept to program.
rickerttrd 2
            
greyline-770



            
Workshop and offices 309 Progress Road, Wacol, Brisbane Qld 4076 • Phone (07) 3879 4300  Fax (07) 3879 4844