Large enough to get things done
               – small enough to get it done right
            
Our projects in 2006
greyline-770

 
            
aibn 1
SHAMROCK TEAM:

Andrew Kerr
Estimator

Paddy O’Boyle / Darren Morris
Site Supervisors

David Carney
Project Manager


            
AIBN, University of Qld
CLIENT:  Abigroup
CLIENT REP: Peter Clarke
CONTACT NO: (07) 3391 7311
VALUE: $1.4 million
DURATION: Nov 2004 – Oct 2006
grey-line

Situated at the University of Queensland St Lucia Campus, the Australian Institute of Bioengineering and Nanotechnology is a cutting edge research facility. Shamrock Civil contract works for the project included bulk excavation, sewer, stormwater and carpark as well as roadworks.

Due to the confined site restrictions a large amount of coordination between Shamrock Civil and the client as well as all other subcontractors on site was essential on a daily basis. Following the initial bulk excavation for the building platform and service tunnel, Shamrock Civil installed a stormwater system comprising of overland flow inlet and outlet structures, reinforced concrete pipes and culverts. The installation of a sewer line and 6 No. sewer structures diverted the existing sewer line in order to allow the construction of the new 6 story building to progress.

All works to the AIBN project were completed on time, within budget and to the highest safety standards.

aibn 2
            
greyline-770


            
brissquare 1
SHAMROCK TEAM:

Liz Kirwan
Estimator

Jim Steward
Site Supervisor

Liz Kirwan
Project Manager 

            
Brisbane Square
CLIENT:  Baulderstone Hornibrook   
CLIENT REP:  Lee Hughes
CONTACT NO:  (07) 3381 9011
VALUE:  $573,000
DURATION:  April – October 2006

grey-line
This 40 story building was constructed on a 7740m2 site which fronts North Quay and the Brisbane River with half of the site devoted to public space.

Shamrock Civil were awarded the External Roadwork & Footpath package.

All demolition was carried out in areas which were abundant with live services without incident. Demolition consisted of the removal of existing concrete and asphalt, removal of redundant services and removal of existing heritage kerb for reuse.

The Road works comprised of the following activities:
  • Construction of road widening at Adelaide St and North Quay.
  • Constructing on new bus inlet bay George St.

The Footpath works comprised of the following activities:
  • Excavating under road, kerb and to the edge of the building slab to required level and placement of roadbase material to form the adjacent slab extending to the back of Kerb.
  • Installation of porphyry kerb and footing
  • Form and install concrete channel

All works were carried out within a small, congested work zone which presented many obstacles throughout the project, however all critical dates were achieved.

brissquare 2
            
greyline-770



            
chermsideculvert 1
SHAMROCK TEAM:

David Byrne
Estimator

Les Nolte / Eamonn Turner
Site Supervisor

David Carney
Project Manager

            
Chermside Culverts
CLIENT:   Westfield Design and Construction
CLIENT REP:  Arron Fischer
CONTACT NO: (07) 3350 1566
VALUE:  $4.7 million
DURATION:  Nov 2005 – April 2006

grey-line
As part of the stage 5 Westfield Chermside expansion, SCE were awarded the contract for bulk excavation works and the installation of a 530m long trunk drainage system to tie into an existing culvert system and divert water from a creek under the proposed new shopping centre extension (stage 5), through a twin cell culvert system/sediment basin and drain into Somerset creek.

The trunk drainage line consisted of 7 No. reinforced concrete structures accommodating a 2.100m dia pipeline and culverts ranging from 3.000 x 2.550m to 4.800m x 3.600m in size.  An insitu reinforced concrete base was constructed using traditional methods of construction and the precast culvert elements ranging from 7t to 13.5t were placed sequentially using a 200T crane to allow for deep excavation conditions.

The largest of the structures on the culvert line, headwall 5/1 was a reinforced concrete structure 21 x 22m with 6 No. columns and a sloped base slab which formed a 1m deep sediment basin to minimise the environmental impact on the creek. The original design was a reinforced concrete roof structure but due to continual poor weather conditions, Shamrock Civil put forward a design proposal for the installation of a precast roof. This proposal was approved and 600mm thick precast roof elements were installed covered with a 100mm structural concrete screed.  

Working within a live creek environment presented many obstacles throughout the duration of the works, however all critical dates and safety standards were achieved.

chermsideculvert 2a
            
greyline-770

 
            
cherminternal 1
SHAMROCK TEAM:

David Byrne
Estimator

Paddy O’Boyle / Eamonn Turner
Site Supervisor

David Carney
Project Manager


            
Chermside Internal Roads
CLIENT:   Westfield Design and Construction
CLIENT REP:  Arron Fischer
CONTACT NO: (07) 3350 1566
ENGINEER:  MPN Engineers
VALUE:  $3.8 million
DURATION:  Feb – Oct 2006

grey-line
As part of the stage 5 Westfield Chermside expansion, SCE were awarded the internal roads and carpark contract. These works involved close coordination with the client to meet their specific critical dates but also to enable continued progress in all areas of the site. The roads package involved both works for Brisbane City Council and Main Roads as well as internal roads and 2 separate ongrade carparks for Westfield Design & Construction direct. Over 1.5km of stormwater lines, approximately 15,000m2 of asphalt pavement and 2000m2 of concrete pavement were placed throughout the site.

The stage 5 expansion will increase the centre from approximately 79,000 sqm to approx. 116,000sqm, making this one of Queensland’s largest regional shopping centres.

"The opening day was a great success, and the complimentary speeches from Mr Stephen Lowry and Mr Bob Jordan at the opening should be passed on to all those involved on just how good the Centre looked from a standard of quality and design benchmark which was delivered on the day."  Allan Robertson, Senior Project Manager

cherminternal 2
            
greyline-770
 
            
aclll 1
SHAMROCK TEAM:

David Byrne
Estimator

Paddy O’ Boyle
Site Supervisor

Liz Kirwan
Project Manager

            
ACLLL Springfield
CLIENT:  Baulderstone Hornibrook
CLIENT REP:  David Layzell
CONTACT NO: (07) 3381 9011
VALUE:  $1.77 million
DURATION: August 2005 – February 2006

grey-line
Shamrock Civil were awarded the civil component for the construction of a new university at Springfield. This work comprised of the construction of 2 roads and 3 carparks.

The initial works comprised of clearing the site of all existing vegetation and the bulk excavation and filling as required. 

Civil storm water included the laying of pipework and construction of various types of concrete structures including a number of gross pollutant traps.

The road works component included the construction of 13,500m2 of asphalt car parks and internal roads, construction of crossovers, speed bumps, footpaths and kerb and channel.

All works were completed on time and to a high quality to meet the requirements of ACLLL and Baulderstone Hornibrook.
aclll 2
            
greyline-770


            
qldairport 1
SHAMROCK TEAM

David Byrne
Estimator

Paul Black
Site Supervisor

Liz Kirwan
Project Manager

            
Tradecoast Central - Qld Airport
CLIENT:  Prime Developments
CLIENT REP:  Cassie Eivers
CONTACT NO:  (07) 3331 7311  
VALUE:  $1.18 million
DURATION:  May 2006 – September 2006

grey-line
Tradecoast Central, located on the former Brisbane Airport site adjacent to the Gateway Arterial Motorway is a joint venture between the Brisbane City Council and Prime Development Corporation which will provide on completion, an area in excess of 110 hectares of a planned industrial community.

Shamrock Civil were awarded the demolition and site preparation package with the main scope of works being the removal and processing of 15,850m3 of existing concrete and 6000m3 of existing asphalt pavements within the site.  

25,000m3 of existing spoil material was located on top of the existing pavements in various locations. It was necessary to remove this material to allow the removal of the pavements in these locations. The fill material was carted from the runway and placed and compacted in accordance with level 1 geotechnical supervision in areas of future development within the Tradecoast central site.

2000m3 of the stockpiled material consisted of acid sulphate affected soils. It was necessary to lime treat this soil on site before it was carted to the fill area.  Bioremediation was required on 1800m3 of soil located at the former Fuel Depot. This consisted of spreading the soil, treating it with fertilizer at 1kg/m3 and turning twice per week for 5 weeks.

All works were completed on time and to a high quality to meet the requirements of Prime Developments.
qldairport 2
            
greyline-770



            
qldmuseum 1

SHAMROCK TEAM

David Byrne
Estimator

John O’Hagan
Site Supervisor

Liz Kirwan
Project Manager


 

            
Qld Museum Refurbishment
CLIENT:  Abigroup  
CLIENT REP:  Troy Holmes
CONTACT NO:  (07) 3391 7311
VALUE:  $200,000
DURATION:  October 2005 – July 2006

grey-line
This heritage listed building was designed and built as an exhibition hall in 1891 and then converted to a museum and subsequently a concert hall. It is located on a 1.5 hectare site at the intersection of Bowen Bridge Road and Gregory Terrace.

Shamrock Civil were awarded the civil and roadworks package component for the refurbishment of the Old Queensland Museum. The initial works included the demolition of existing asphalt, concrete and redundant services. As this is a heritage listed building, it was vital that all demolition works were carried out with the utmost care to ensure no damage was caused to the building structure.

As part of our works it was necessary to install 150m of stormwater line and associated pits.   As this is an existing building, the stormwater works were completed under difficult conditions including boring under existing services and excavation in rock.

Other works included:
• Replacement of Roadway
• Replacement of Kerb and Channel
• Concrete parking bays

The concert hall remained operational during the work, so it was vital that works were programmed and executed to cause minimal disruptions.
qldmuseum 2
            
greyline-770



            
portside

SHAMROCK TEAM

David Byrne
Estimator

John Esler
Site Supervisor

Callan Stephens
Project Manager


 

            
Multiplex - Portside
CLIENT:   Multiplex
CLIENT REP:  Megan Conlon
CONTACT NO:  (07) 3868 2499
VALUE:   $1.83 million
DURATION:  October 2005 – August 2006
grey-line
Project scope included all civil infrastructure upgrades required for the Portside Wharf Development.  All works were completed on existing roads with public and construction traffic flow being maintained at all times.

Major roadworks were carried out to a number of streets surrounding the site including the upgrading of the intersection of Kingsford Smith Dr and Remora Rd. Works included the removal and replacement of existing road pavements, concrete works, and retaining wall installation all in co-ordination with traffic light upgrades.

Major stormwater and sewer infrastructure works were completed under difficult site conditions including a major redesign mid project. 2100 dia stormwater culverts were installed at a maximum depth of 5m in flowing sand. All works were completed on time and budget and to a high quality to meet the requirements of the Portside Wharf Development.

portside-pics
            
greyline-770
 
            
grandplaza 1
SHAMROCK TEAM:

Anthony Hallagan
Estimator

Nick Sandwell
Project Manager

Carl Eaton
Site Supervisor



            
Grand Plaza - Browns Plains
CLIENT:  Watpac
CLIENT REP:  Greg Reinke
CONTACT NO:  (07) 3839 6748
VALUE:  $1.4 million
DURATION:  August 2005 – October 2006
grey-line
Grand Plaza is a large sub-regional shopping centre located on Grand Plaza Drive, Browns Plains. Grand Plaza is host to some of Queensland’s largest retailers such as Big W, Target, Kmart, Best & Less, Woolworths, Coles, Birch Carroll & Coyle and Aldi. The Shopping Centre underwent a major expansion mid 2005 which was completed and successfully opened in September 2006.

The works carried out by Shamrock Civil Engineering at Grand Plaza were managed as two separate contracts; Bulk Earthworks and Road-works.

The Bulk Earthworks Sub-contract comprised the following major activities:
•  Demolition of an existing car park (approx 11,500m2).
•  Bulk Excavation (approx 12,000m3) for the new Building Pad.
•  Retention works consisting of 500m2 of shotcrete and 300 rock anchors
•  Bored concrete piers to enable the new building to span over a major storm-water culvert.

The Roadworks Sub-contract comprised of the following major activities:
•  New turning lane on Grand Plaza Drive to provide access into the new suspended carpark.
•  New roundabout on Grand Plaza Drive.
•  Reconfiguration of existing Eastern Car Park and entry road.
•  Bulk Earthworks and reconfiguration of existing Western Car Park to suit new building.

The works were carried out in a delicate and professional manner to ensure that the Shopping Centre operated successfully and uninterrupted throughout the full duration of the project.

grandplaza 2
            
greyline-770



            
Workshop and offices 309 Progress Road, Wacol, Brisbane Qld 4076 • Phone (07) 3879 4300  Fax (07) 3879 4844