Large enough to get things done
               – small enough to get it done right
            
Our projects in 2007
greyline-770

 
            
            
princecharles 1
SHAMROCK TEAM:

Liz Kirwan
Estimator

Alex Geuna
Site Supervisor

Liz Kirwan
Project Manager


            
Prince Charles Hospital
CLIENT:   Baulderstone Hornibrook
CLIENT REP:  Lee Hughes
CONTACT NO:  (07) 3256 4933   
VALUE:   $743,000
DURATION:   June 2006 – May 2008
grey-line

In February 2007 Queensland Health opened a new Department of Emergency Medicine at the Prince Charles Hospital Brisbane. Shamrock Civil were awarded the External Civil and Roadworks package for this stage of the Prince Charles Hospital upgrade.
The initial works included the demolition of existing asphalt, concrete, and retaining wall. All demolition and excavation works were carried out in areas containing live services running to the existing hospital.
The roadworks component included:
·         Detailed Excavation
·         Placement of asphalt for new road and carpark
·         Placement of concrete pavement and kerbs
Other works included the installation of stormwater and the reconstruction of a 20m x 2m service trench.
 
As part of the Prince Charles Hospital upgrade Stage 2B & C, Shamrock Civil were engaged to carry out a widening of First Avenue to convert it from a one-way to a two-way road. These works included the construction of new asphalt pavement and retaining wall through existing garden beds which contained many live services.
 
As both the Prince Charles Hospital and Holy Spirit Hospital remained operational it was essential that the works did not affect the functionality of the hospital departments.
princecharles 2
            
greyline-770

 
            
brisintair 1
SHAMROCK TEAM:

David Byrne
Estimator

Carl Eaton / Paddy O’Boyle
Site Supervisors

Callan Stephens / Declan Hughes
Project Managers


            
Brisbane International Airport Upgrade
CLIENT:   Bovis Lend Lease
CLIENT REP:  Bill Timms / Richard Horton
CONTACT NO:  (07) 3225 7100
VALUE:  $6.8 million
DURATION:  October 2006 – May 2007
grey-line
The Brisbane International Airport Expansion Project consisted of two separate construction sites, the Northern Concourse and the ITBX extension.All works carried out on each Construction Site were preformed in accordance with The Strict Regulations of Brisbane Airport Commission and Bovis Lend Lease.
 
Due to the volume of material being moved from each site & the volume of Traffic expected, a detailed Traffic Management plan was put in place prior to the commencement of works.

The Construction of the Temporary Access Roads comprised the following:
•  Demolition of existing road shoulders.
•  Construction of roads on sand.
•  Shaping of Embankments to form Swale Drains,
•  Placement of Ironman Barriers to separate Airport Traffic from Construction Traffic

The Bulk Earthworks comprised the following:
•  Demolition of existing Car Parks and Runway Aprons.
•  Transplanting Existing Trees off site.
•  Bulk Excavation (Approx 81,500m_) for the New Building Platforms.
•  Install Construction Hardstands to Building Platforms.

Excavation of the Super Trench comprised the following:
•  Installation of a Spear System to dewater the trench prior to commencement of excavation.
•  The trench excavation was 7m deep and 30m wide at the top of batters.

Storm water works consisted of the following activities:
•  Laying of Storm water lines for new extension at the Northern Concourse.
•  Connection to Existing Storm water lines.

Alterations to Baggage Handling Roads consisted of the following activities:
•  Widen existing baggage road.
•  Line marking alterations.
•  Landscaping.

The works here had to be carried out on airside, which meant having security in place at all times.  Because this road was still active the works had to be carried out as to not disturb the flow of Airport Traffic during the busy hours.  This meant most activities had to happen out of hours.
brisintair 2
            
greyline-770

 
            
greyst 1
SHAMROCK TEAM:

David Byrne
Estimator

Derek Hennessy
Site Supervisor

Nick Sandwell
Project Manager


            
Tribune on Grey Building , Southbank
CLIENT:  W.A. Stockwell Pty Ltd
CLIENT REP:  Shane Percy
CONTACT NO:  (07) 3033 9320  
VALUE:   $2.3 million
DURATION:   June 2006 – March 2007

grey-line
The Tribune on Grey Building is a $65 million commercial office building positioned on the corner of Grey and Tribune St, Southbank. The building includes 12,000 square metres of commercial space, with some ancillary uses, and is designed to accommodate the goals of the Southbank Corporation for Grey Street.

Shamrock Civil were contracted by Stockwell to carry out bulk earthworks, bored piers, retention and decontamination of the site. The bulk earthworks included clearing and stripping the site and excavation to basement level to a depth of approximately 6 metres beneath the existing road level. The perimeter of the site and adjoining properties were retained by a series of contiguous bored piers, whalers and rock anchors. Once the structure of the building was completed the anchors and whaler were de-stressed and removed from site. Throughout the course of the work, the site was selectively decontaminated under geotechnical and environmental supervision to enable the site be removed from the Contaminated Land Register.

The Tribune on Grey Street project comprised complicated and detailed works that took place on a small and heavily congested site. The project was delivered to the client successfully due to the preliminary planning and teamwork between Shamrock Civil and Stockwell.
tribune 2
            
greyline-770

 

 

            
raaf 1

SHAMROCK TEAM:

David Byrne
Estimator
 
Les Nolte/Graham McManmon
Site Supervisors
 
Callan Stephens
Project Manager


 


            

RAAF Amberley Runway

CLIENT:  QR Concrete / Leightons
CLIENT REP: Aiden McSkimmings
CONTACT NO: (07) 3632 1400
VALUE:  $2.6 million
DURATION: April 2006 – April 2007
grey-line
The project comprised of the demolition & removal of approx. 50,000m2 of existing runway concrete. The existing subgrade was then further excavated & prepared to accept specialised pavements which were paved with a paving machine to required specifications to accept the new concrete runway.
 
The removal of the concrete pavements within the existing concrete runway had to be lifted out without damaging the adjacent existing concourse. A specialized lifting was used to ensure the adjacent slabs were not damaged.
 
The works were carried out within an existing & operational runway with timely handover of works being a major requirement of the airforce base.
raaf 2
            
greyline-770


            
strathblane 1

SHAMROCK TEAM:

David Byrne
Estimator

Luke Corcoran
Site Supervisor

Liz Kirwan
Project Manager

 


            
Strathblane Gas Plant – Spring Gully
CLIENT:  Origin Energy
CLIENT REP:  Adam Mann
CONTACT NO:  (07) 3858 0702
VALUE:  $1.8 million
DURATION:  Oct 2006 – Sept 2007
grey-line
The Spring Gully development project is located approximately 80km north of Roma in central Queensland. It is the fourth stage of the development of the Spring Gully gas field.

Shamrock Civil were the contractors appointed to supply the materials, labour and plant for the construction of earthworks associated with the Strathblane gas plant site.

These works comprised of:
  • Excavation of 40,000m3 of unsuitable silty sand material, haul to stockpile and compact and trim to neat profiles.
  • The construction of a treated water evaporation pond, 33m x 33m x2.5m involving 1,000m3 cut and 3,000m3 fill.
  • The construction of a produced water storage pond, 92m x 131m x 3m involving 22,500m3 cut and 22,200m3 fill.
  • Earthworks/benching associated with the gas plant site, covering an area of 20,000m2 involving 21,600m3 cut and 12,100m3 fill.
  • Haulage and spreading of 4,600m3 of topsoil.
  • The construction of a 12,000m2 reverse osmosis plant involving 4,000m3 cut and 10,000m3 fill.

All works were completed on time and to a high quality to meet the requirements of Origin Energy.
strathblane 2
            
greyline-770



            
riverlinks 1
SHAMROCK TEAM:

David Byrne
Estimator
 
Paddy O’Boyle
Site Supervisor
 
Liz Kirwan
Project Manager


            
Ipswich Riverlinks Shopping Centre - External Roads, Stage 1
CLIENT:   Leda Design & Construction
CLIENT REP:  Wayne Holborow
CONTACT NO:  (02) 8226 4444
VALUE:  $1.5 million
DURATION:  February 2007 – July 2007

grey-line

Riverlinks Shopping Centre is a new development located in the northern area of Ipswich CBD. The shopping centre which opened it doors on April 5th 2007 is host to some of Queensland’s largest retailers such as K-mart, Target, Coles and Woolworths as well as over 100 specialty stores.
 
As part of the development, Shamrock Civil was awarded the external roads contract which involved works for both Ipswich City Council and Main Roads. The work comprised of the demolition and reconstruction of The Terrace and Downs Street and the upgrading of the intersection of Lowry Street and Downs Street to meet the requirements of the new shopping centre. The contract also included the construction of 2 main entrances to the shopping centre.
 
The External Roads Contract comprised of the following major activities:

  • Demolition of existing asphalt (approx 3,500m2)
  • Demolition of existing concrete (approx 1,000m2)
  • Excavation for new pavement Placement of storm water pipes and structures. 
  • Construction of new asphalt pavement (approx 4,100m2)
  • Construction of new concrete footpath (approx 1,200m2)

As many local businesses are located on The Terrace and Downs Street, it was essential to maintain one way traffic at all times to allow the businesses to operate successfully and uninterrupted throughout the duration of the works.

riverlinks 2
            
greyline-770



            
amberley 1
SHAMROCK TEAM:

Andrew Kerr
Estimator

Graham McManmon
Site Supervisor

Craig Jack
Project Manager

            
Amberley Sewer Pit and GPT
CLIENT:  Baulderstone Hornibrook  
CLIENT REP:   Dhjango Henry
CONTACT NO:  (07) 3237 6139
VALUE:  $585,000
DURATION: April 2007 – September 2007
grey-line
Baulderstone Hornibrook awarded Shamrock Civil the contract of the Civil works, construction of the Pump Station and Gross pollutant trap as part of the RAAF Amberley Stage 2 Re-development works.

The staging of this 10m deep excavation in a limited space was crucial in planning of this project. The top half of the excavation was benched down with the final 5meters utilising a power brace system to ensure safety of the workers.

Use of pre-cast manhole rings and casting of sections into the base at ground level was seen as the most efficient manner of construction. This 38T base was then lifted into position and built up to the finished surface level.

Finally the Sewer Pit was coated with Megapoxy and patched after final fitting of the Pump Station.

The Gross pollutant trap was constructed to divert water flowing down Stormwater channel throughout the RAAF base and remove contaminants.

We placed and fixed the pre-fabricated sections, formed and poured the weir wall then finished off the site by installing the rock protection.

amberley 2
            
greyline-770


 
            
rqys 1

SHAMROCK TEAM:

Craig Jack
Estimator

Darren Morris
Site Supervisor

Craig Jack
Project Manager


 

            
RQYS Pump Station
CLIENT:  Royal Qld Yacht Squadron
CLIENT REP:   Jane Meaney
CONTACT NO:   (07) 3334 8500
VALUE:   $216,000.00
DURATION:   November 2007 – December 2007
grey-line
RQYS engaged Shamrock Civil Engineering to provide them with a pump station for the upgrade of their sewer services in line with their upgrade and expansion of the existing club.

Due to the ground conditions on this occasion we utilized a caisson style construction method whereby we benched the excavation down about a meter placed the first section, excavated within the caisson then pushed the caisson down into the excavation. Once the next section was placed the same was done until we had the caisson at the correct height then poured the base then the roof.
The sewer pit was coated and the penetrations patched after the plumbers fitted out the pit.

Whilst this job could have been potentially hazardous with respects to Groundwater, Acid Sulphate soils, co-ordination with other Trades, and working within 15m of the entrance to the club. Shamrock was able to bring this project in below budget, and in an expedient manner that exceeded the customer’s expectations.

The client was very happy with the efficiency and expedient manner in which we completed this project enabling them to utilize the area over the festive season.
rqys 2
            
greyline-770



            
Workshop and offices 309 Progress Road, Wacol, Brisbane Qld 4076 • Phone (07) 3879 4300  Fax (07) 3879 4844