|
|
Large enough to get things done
– small enough to get it done right
|
|
| | | | | | | | | | | | | |
| | |
 |
|
SHAMROCK TEAM:
Julia Nest Estimator
Darren Morris Site Supervisor
Sean Keane Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: CS Energy CLIENT REP: Naidu Rajnesh CONTACT NO: 07) 3810 8612 VALUE: $150,000 DURATION: February – March 2008 |
|
 |
Shamrock Civil was contracted by CS Energy for the construction of a concrete spillway for the Ash Dam at Swanbank Power Station. Shamrock’s package also included the demolition of the existing concrete spillway, the reshaping of the existing batters, grading and leveling of the access roads and the spreading of chitters on the access roads. The dam works also included dumped rock protection and a reno mattress.
Shamrock Civil also carried out a number of smaller tasks for CS Energy whilst on site including the relocation of the existing dam overflow pipe and the installation of a new overflow pipe and alterations to the access roads and batters. Shamrock Civil were able call upon their extensive resources to ensure we were able meet CS Energy’s additional needs whilst still completing the project within the original programme.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
David Byrne Estimator
Sean Lucas Site Supervisor
Liz Kirwan Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
Railway Terrace, Ebbw Vale |
|
CLIENT: Southern Regional Water Pipeline CLIENT REP: Breneke Steyl CONTACT NO: (07) 3535 8533 VALUE: $476,000 DURATION: April 2008 – May 2008
|
|
 |
The Southern Regional Water Pipeline will take the combined water from Wivenhoe Dam, Hinze Dam, the Tugun desalination plant and future water sources to where it is most needed across five South East Queensland councils. A portion of this 100km pipe line runs along Railway Street, Ebbw Vale. Shamrock Civil were awarded the contract to carry out a full reconstruction of Railway Street once the pipeline was installed. The Contract comprised of the following major activities:
- Demolition of existing asphalt (approx 3,000m2)
- Excavation for new pavement Placement of 160m of storm water pipes and associated structures.
- Construction of new asphalt pavement (approx 3,000m2)
- Construction of new concrete footpath and driveways (approx 100m2)
- Landscaping (approx 220m2)
As there are many residential properties and a popular soccer club located on Railway Street, it was essential to maintain local access at all times. All works were programmed and executed to cause minimal disruptions to resident and patrons.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
David Byrne Estimator
Les Nolte Site Supervisor
Sean Keane Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
West Pacific Pines State School
|
|
CLIENT: Northbuild CLIENT REP: Andrew Packer CONTACT NO: (07) 3373 6100 VALUE: $1.97 million DURATION: May 2007 – January 2008
|
|
 |
Northbuild Constructions awarded Shamrock Civil the Earthworks, Stormwater and Pavements contracts for the West Pacific Pines State School in May 2007.
The stormwater involved the construction of stormwater lines ranging in size from 300-900 diameters, the associated manholes and access chambers, and the installation of 4no Gross Pollutant Traps
Shamrock Civil also carried out the bulk excavation for retaining walls, 5000m3 of cut and fill, the preparation and leveling of 3300m2 of building pads and the back filling of the retaining walls.
The contract also involved the construction of link walls, filling on landscape batters, filling behind the link walls and the trimming of 29,000m2 of landscape areas. Shamrock utilised their extensive experience to ensure the filling behind the link walls and the filling on the landscape batters were carried out safely and without incident.
The contract also consisted of 6500m2 of asphalt car park and the associated line marking and road signage.
Shamrock Civil liaised closely with Northbuild Constructions to ensure all portions of the project were completed and handed over on programme as required to allow for the opening of the school for the 2008 school year. |
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
Julia Nest Estimator
Declan Hughes / Carl Eaton Site Supervisor
Sean Keane Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: Northbuild CLIENT REP: John Liddington CONTACT NO: (07) 3373 6100 VALUE: $1.16 million DURATION: May 2007 – April 2008 |
|
 |
Northbuild Constructions awarded Shamrock Civil the civils package for the Queensland Combined Emergency Services Academy (QCESA) project at Whyte Island Brisbane. The works included groundworks, demolition, stormwater, 4800m2 of pavements, subsoil drainage, electrical and communications conduits and light and camera pole footings The project also comprised of 6no 6m deep tanks to harvest the water from fire fighting exercises and a Gross Pollutant Trap. Shamrock constructed the intricate subsoil drainage system and drainage layers required to harvest the water. The project also included a spillway area in which Shamrock carried out the detailed and complex shaping required to simulate a chemical spill and the associated culverts and stormwater to harvest the water. Shamrock Civil were able to call upon there extensive range of resources to meet Northbuild’s accelerated programme. Both stages of the project were handed over on programme to the client’s satisfaction.
|
|
 |
|
| | | | | | | | | | | | | |
| | | |
 |
|
SHAMROCK TEAM:
David Byrne Estimator John Esler, Les Nolte, John O’Hagan & Damien Goodwin Site Supervisors Nick Sandwell Project Manager Bevon Peddell Project Coordinator
|
|
|
|
|
| | | | | | | | | | | | | |
Arthur Gorrie Correctional Centre Expansion & Brisbane Reception Centre Expansion |
|
CLIENT: Bovis Lend Lease (Department of Corrective Services) CLIENT REP: Ron Melton / David Flood CONTACT NO: (07) 3271 1445 VALUE: $7million DURATION: August 2006 – May 2008
|
|
 |
The objective of the correctional centre projects was to provide the Brisbane Reception Centre (BRC) and Arthur Gorrie Correctional Centre (AGCC) with increased cell accommodation and upgrades to the supporting services and infrastructure. While the BRC was non-operational during construction, AGCC was fully operational and required Shamrock Civil to operate within the strict site rules and protocols as set out by BLL and GEO (Arthur Gorrie Centre Management). Works at the Arthur Gorrie Correctional Centre included:
- Clearing and demolition of redundant services and pavements
- Bulk excavation and reinstatement of uncontrolled fill to construct building pads for new cell blocks and administrative blocks.
- Retaining walls and concrete walkways.
- Stormwater and Sewer Drainage including tunnel boring under the external security fence, construction of a 100kL plastilined precast sewer storage facility and connection into existing sewer pump station
- Roadworks for new asphalt surfaced visitor carpark and remedial works to the existing visitor carpark and security surveillance ring road.
Works at the Brisbane Reception Centre included:
- Bulk Earthworks to construct building pads for new cell blocks, administration and visitor processing buildings.
- Construction of 224 x 600mm diameter reinforced concrete bored piers for building foundations
- Stormwater Drainage
- Roadworks for new asphalt surfaced visitor carpark
- Approximately 70,000m2 of turfed landscaping
The works were completed and handed over on time without disruption to the operation of the correctional centre facilities.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
Julia Nest Estimator Jim Steward Site Supervisor James Kennedy Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: Watpac CLIENT REP: John O’Kane CONTACT NO: (07) 3251 6321 VALUE: $818K DURATION: November 2007 – February 2008
|
|
 |
Brisbane Boys' College is an independent day and boarding school for boys, located in Toowong. Shamrock Civil were awarded the External Civil and Roadworks package for the redevelopment of the College. The external civil and roadworks consisted of new internal roads, car park and bus set down area and modifications to Moggill road and Miskin Street entrances. This work involved: · The demolition of 3500m2 of existing road. Demolition of kerb, channel, crossovers, stormwater pipes and pits. · Installation of 150m stormwater pipes and associated manhole and inlet structures. · Concrete works which included approx 1200m of and channels(including subsoils), approx 380m2 of footpaths and two concrete roundabout infills.. · Two crossovers were also constructed, one at Moggill road one at Miskin Street · Construction of 3800m2 of new asphalt pavement. The new road was constructed parallel to the Toowong Creek, therefore it was essential maintain a high standard of silt management and environmental control to ensure the river remained free from any debris or contaminates. Shamrock Civil worked closely with Watpac and the Brisbane boys college to ensure all works were carried out in a delicate and professional manner to ensure that the school operated successfully and uninterrupted throughout the full duration of the project. All works were carried out to in accordance with Brisbane City Council Standards and completed on time and within budget.
|
|
 |
|
| | | | | | | | | | | | | |
| | | |
 |
|
SHAMROCK TEAM:
David Byrne Estimator Derek Hennessy Site Supervisor Craig Jack Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: FKP CLIENT REP: Daniel Deans CONTACT NO: (07) 3334 8500 VALUE: $ 1.7m DURATION: August 2007 – August 2008
|
|
 |
FKP engaged Shamrock Civil Engineering to do the bulk excavation and facilitate the Top Down construction of 3 basement levels for Matisse Towers in Mary St, Brisbane. Combining the contaminated and constricted site with the Top Down construction and high level of co-ordination this job certainly possessed its fair share of potential issues. The construction process involved preparing each level to have the slab poured. Once the slab was poured and cured SCE commenced the excavation and then under-mining of each level until the surface below was prepared for the concurrent slab. During this process SCE would remove the bulk of the material, scabble the walls, columns and roof where necessary, and demolish the lift pit over pour. SCE would then prepare any rebates or recesses and prepare the slab and then allow the concreters to pour the next slab. As well as the restricted space and the potential safety issues apparent with a job like this, SCE also utilized specialized machinery to extract material up to 10m through the centre of the site in order to load Trucks on the top slab and remove the material.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
David Byrne Estimator Darren Morris Site Supervisor Sean Keane Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: Woollam Construction CLIENT REP: Ian Morris CONTACT NO: (07) 3456 1600 VALUE: $ 500k DURATION: May 2008 – August 2008
|
|
 |
Shamrock Civil were contracted by Woollam Constructions to carry out the earthworks, pavements and stormwater works at the City Beach factory extension. The project consisted of the construction of the new stormwater lines, the associated structures, the installation of a Gross Pollutant Trap and the construction of a bio retention basin. Shamrock Civil also constructed 14m of 2700x1500 culverts to allow for the new entrance to the warehouse. These works were carried out whilst maintaining effective environmental and silt controls to protect the live creek. Shamrock also carried out the earthworks and the construction of a new 6100m2 building pad. These works were staged so as to allow the warehouse to remain fully operational during construction. The construction of the new asphalt internal road was also part of Shamrock Civil’s package. Shamrock Civil completed the project to the satisfaction of Woollam Constructions and on programme whilst allowing for the staging required to allow for the warehouse to remain open during construction.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
James Kennedy Estimator Paddy O'Boyle Site Supervisor James Kennedy Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
|
CLIENT: John Holland CLIENT REP: Peter Furlong CONTACT NO: (07) 3867 7000 VALUE: $ 560k DURATION: Aug 2008 - October 2008
|
|
 |
Southbank Institute of Technology lies in the heart of Brisbane’s Southbank district. It is Queensland's leading Institute of TAFE with more than 27,000 students enrolled. Since 2005, the Institute has been engaged in a $550m redevelopment project to create a world-class facility at its Southbank campus. Running through the heart of the TAFE campus is the Educational Pathway. Starting at Glenelg St. the pathway runs through Ernest St. to connect to Turbine St. on the opposite side of the campus. This connects Block E and Block C of the college together.
The package awarded to SCE was split into two stages. Stage 1 was the construction of a 700m2 visitor’s carpark located in the campus grounds, adjacent to Merivale St. Stage 2 comprised of the redevelopment of Ernest Street between Merivale St. and Colchester St.
Stage 1 works began at the end of August and comprised of: · The demolition and excavation of existing services in the carpark · Installation of 50m of Stormwater pipes, including construction of new pits and connections to existing. · Construction of 150m of Kerb, including subsoil’s to suit · Construction of 700m2 of Asphalt pavements, followed by linemarking and installation of signage.
Stage 2 works involved a full road closure. This had to be coordinated with John Holland and the Brisbane City Council to ensure there would be no clash with the River Fire festival. Stage 2 works started in early September after River Fire and ran concurrently with Stage 1. Works comprised of: · Location of existing services · Demolition of existing pavement, kerb and footpaths and preparation for new pavement · Installation of 80m of Stormwater pipes, including construction of new pits and connections to existing services. · Installation of 30m of ACO polycrete custom stainless steel grate and frame. · The Road was constructed from both asphalt and concrete and included ramps at either end. · Concrete works included placing colour concrete and placing an exposed concrete. · Thermoplastic linemarking and signage
For the duration of the project safety was the main priority for persons working on site and for the public and students passing by the site every day. The project was completed on budget and Ernest Street was reopened according to the program set by Brisbane City Council.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
David Byrne Estimator Luke Corcoran Site Supervisor Liz Kirwan Project Manager
|
|
|
|
|
| | | | | | | | | | | | | |
Spring Gully Development - Taloona Gas Plant Access |
|
CLIENT: Origin Energy CLIENT REP: Adam Mann CONTACT NO: (07) 3858 0702 VALUE: $ 3 million DURATION: June 2008 - December 2008
|
|
 |
The Spring Gully development project is located approximately 80km north of Roma in central Queensland. As part of the fifth stage of the development of the Spring Gully Gas Field, it was necessary to construct a new road to the natural gas compressor plant on the Taloona property.
Shamrock Civil were the contractors appointed to supply the materials, labour and plant for the construction of over 6km of primary sealed road linking the Taloona Gas Plant to the existing public road (Wybara Road).
These works comprised of:
- Strip and grade 20m wide track for the proposed 6km length of road.
- Demolition and removal of old existing creek crossings, motor grids and fencing.
- Earthworks and subgrade preparation for the construction of the 6km road formation. (50,000m3 cut to fill & 15,500m3 cut to spoil)
- Bituminous surfacing (45,000m2)
- Construction of culverts (both box and pipe – including R.C. footings, slabs, walls, wing-walls, head-walls and aprons), flood ways and scour protection.
- Embankment and slope stabilization including the supply and installation of shotcrete, rock pitching and grouted rock pitching, rock check-dams (slopes / cut off drains / side drains)
- Supply and installation of all road fixtures, flood level markers, regulatory signage, guardrails and terminals.
- Respread, seeding and fertilizing of topsoil to drains, gullies, embankments and batters (20,000m2)
- Maintenance and upkeep of the temporary Gas Plant access road during the works to maintain a safe traffic flow.
|
|
 |
|
| | | | | | | | | | | | | |
| |
 |
|
SHAMROCK TEAM:
David Byrne Estimator Alex Geuna, Jim Steward, John Esler, Eamonn Turner, Sean Lucas Site Supervisors Liz Kirwan & David Carney Project Managers
|
|
|
|
|
| | | | | | | | | | | | | |
Salisbury to Kuraby Rail Upgrade |
|
CLIENT: S2K Alliance CLIENT REP: Eugene Newman CONTACT NO: (07) 3457 4404 VALUE: $ 8.2 million DURATION: December 2006 - January 2008
|
|
 |
The Salisbury to Kuraby Rail Upgrade was delivered by the S2K Alliance, a partnership between QR Limited and Abigroup Contractors. The works consist of 9.5km of new track and the upgrade of 7 stations. Shamrock Civil were awarded the Carparks, Roadworks and Stormwater Drainage contract for Altandi, Coopers Plains, Fruitgrove, Kuraby, and Runcorn Station. The Contract comprised of the following major activities: Demolition & removal of existing carparks, roads, stormwater and services.
- Demolition & removal of existing carparks, roads, stormwater and services.
- 4,700m3 of bulk excavation.
- 4,500m3 of bulk fill.
- 16,500m3 of detailed excavation for roadworks.
- Placement of over 26,000m2 of new pavement, consisting of 16,000m3 of roadbase and over 3000 tonne of asphalt.
- Construction of 8,200m2 of coloured concrete paving, feature paving, concrete footpath & concrete driveway & kerb ramps.
- Placement of 5,300m of kerb and channel.
- Construction of 2 asphalt roundabouts and numerous concrete traffic islands.
- Laying of 1,300m of reinforced concrete stormwater pipes and 75 stormwater structures including Gross Pollutant Traps, manholes, field inlets & gully pits.
- 3,200m of subsoil drains
- Placement of over 3,500m of underground communication & electrical conduits & 170 associated pits.
- Construction of over 100 street light pole footings.
- Road signage, linemarking, speed bumps, traffic bollards & fencing.
- Topsoiling and soft landscaping.
A large proportion of the road works were carried out on roads which carry high traffic volumes. Works to the Beenleigh Road and Henley Street required a large amount of traffic management and staging in order to construct new pavements, concrete islands, a roundabout and traffic signal works with out disrupting the flow of traffic. As all stations remained operational for the duration of the project the works were programmed to ensure no disruption was caused to the public or railway. Shamrock Civil completed the project on time and to the satisfaction of the S2K Alliance.
|
|
 |
|
| | | | | | | | | | | | | |
| | | |
Workshop and offices 309 Progress Road, Wacol, Brisbane Qld 4076 • Phone (07) 3879 4300 Fax (07) 3879 4844
|
|
|
| | | | | | | | | | | | | |
|
|