Large enough to get things done
               – small enough to get it done right
            
Our projects in 2008
greyline-770

 
            
            
ashdam 1
SHAMROCK TEAM:

Julia Nest
Estimator

Darren Morris
Site Supervisor

Sean Keane
Project Manager




            
Ash Dam Spillway
CLIENT:  CS Energy
CLIENT REP:  Naidu Rajnesh
CONTACT NO:  07) 3810 8612
VALUE:  $150,000
DURATION:  February – March 2008
grey-line

Shamrock Civil was contracted by CS Energy for the construction of a concrete spillway for the Ash Dam at Swanbank Power Station. Shamrock’s package also included the demolition of the existing concrete spillway, the reshaping of the existing batters, grading and leveling of the access roads and the spreading of chitters on the access roads. The dam works also included dumped rock protection and a reno mattress.

Shamrock Civil also carried out a number of smaller tasks for CS Energy whilst on site including the relocation of the existing dam overflow pipe and the installation of a new overflow pipe and alterations to the access roads and batters. Shamrock Civil were able call upon their extensive resources to ensure we were able meet CS Energy’s additional needs whilst still completing the project within the original programme.

ashdam 2
            
greyline-770

 
            
railwaytce 1
SHAMROCK TEAM:

David Byrne
Estimator

Sean Lucas
Site Supervisor

Liz Kirwan
Project Manager


            

Railway Terrace, Ebbw Vale

CLIENT: Southern Regional Water Pipeline
CLIENT REP: Breneke Steyl
CONTACT NO: (07) 3535 8533
VALUE: $476,000
DURATION: April 2008 – May 2008
grey-line

The Southern Regional Water Pipeline will take the combined water from Wivenhoe Dam, Hinze Dam, the Tugun desalination plant and future water sources to where it is most needed across five South East Queensland councils.
 
A portion of this 100km pipe line runs along Railway Street, Ebbw Vale. Shamrock Civil were awarded the contract to carry out a full reconstruction of Railway Street once the pipeline was installed.
 
The Contract comprised of the following major activities:

  • Demolition of existing asphalt (approx 3,000m2)
  • Excavation for new pavement Placement of 160m of storm water pipes and associated structures. 
  • Construction of new asphalt pavement (approx 3,000m2)
  • Construction of new concrete footpath and driveways (approx 100m2)
  • Landscaping (approx 220m2)  

As there are many residential properties and a popular soccer club located on Railway Street, it was essential to maintain local access at all times. All works were programmed and executed to cause minimal disruptions to resident and patrons.



 




railwaytce 2
            
greyline-770

 

            
westpacific 1
SHAMROCK TEAM:

David Byrne
Estimator

Les Nolte
Site Supervisor

Sean Keane
Project Manager


            
West Pacific Pines State School
CLIENT:  Northbuild
CLIENT REP:  Andrew Packer
CONTACT NO:  (07) 3373 6100
VALUE:  $1.97 million
DURATION:  May 2007 – January 2008
grey-line
Northbuild Constructions awarded Shamrock Civil the Earthworks, Stormwater and Pavements contracts for the West Pacific Pines State School in May 2007.

The stormwater involved the construction of stormwater lines ranging in size from 300-900 diameters, the associated manholes and access chambers, and the installation of 4no Gross Pollutant Traps

Shamrock Civil also carried out the bulk excavation for retaining walls, 5000m3 of cut and fill, the preparation and leveling of 3300m2 of building pads and the back filling of the retaining walls.

The contract also involved the construction of link walls, filling on landscape batters, filling behind the link walls and the trimming of 29,000m2 of landscape areas. Shamrock utilised their extensive experience to ensure the filling behind the link walls and the filling on the landscape batters were carried out safely and without incident.

The contract also consisted of 6500m2 of asphalt car park and the associated line marking and road signage.

Shamrock Civil liaised closely with Northbuild Constructions to ensure all portions of the project were completed and handed over on programme as required to allow for the opening of the school for the 2008 school year.
pacificpines 2
            
greyline-770
 
            
whyteisland 1
SHAMROCK TEAM:

Julia Nest
Estimator

Declan Hughes / Carl Eaton
Site Supervisor

Sean Keane
Project Manager


            

QCESA - Whyte Island

CLIENT:  Northbuild
CLIENT REP:  John Liddington
CONTACT NO:  (07) 3373 6100
VALUE:  $1.16 million
DURATION:  May 2007 – April 2008
grey-line
Northbuild Constructions awarded Shamrock Civil the civils package for the Queensland Combined Emergency Services Academy (QCESA) project at Whyte Island Brisbane.
 
The works included groundworks, demolition, stormwater, 4800m2 of pavements, subsoil drainage, electrical and communications conduits and light and camera pole footings   The project also comprised of 6no 6m deep tanks to harvest the water from fire fighting exercises and a Gross Pollutant Trap. Shamrock constructed the intricate subsoil drainage system and drainage layers required to harvest the water. The project also included a spillway area in which Shamrock carried out the detailed and complex shaping required to simulate a chemical spill and the associated culverts and stormwater to harvest the water.
 
Shamrock Civil were able to call upon there extensive range of resources to meet Northbuild’s accelerated programme. Both stages of the project were handed over on programme to the client’s satisfaction.
whyte-island 2
            
greyline-770
 
 
            
morayfield 1
SHAMROCK TEAM:

David Byrne
Estimator

Graham McManmon
Site Supervisor

Craig Jack
Project Manager


            

Morayfield Shopping Centre Roadworks

CLIENT:  LEDA Design & Construction
CLIENT REP:  Wayne Holborow
CONTACT NO:  (02) 8226 4405
VALUE:  $1.1 million
DURATION:  September 2007 - April 2008
grey-line
LEDA engaged Shamrock Civil Engineering to conduct the roadworks adjacent to their Shopping Centre including:
 
·       Widening /Reducing Median Widths
·       Extending Turning Lanes
·       Stormwater pits and pipes
·       Conduits
·       Constructing Pavements
·       New Traffic intersection outside the centre itself
 
Due to the fact that this is the major road through the area carrying high volumes of traffic and the stringent Main roads standards meant that this project offered many complex issues. Some of which include issues in relation to traffic control, staging, co-ordination and managing the job throughout the duration of the Christmas trading period.
 
Close Co-ordination with Utilec to complete the Energex conduits was critical in the provisioning of this project.
 
The client was very happy with the efficiency and expedient manner in which we completed this project.
morayfield 2
            
greyline-770
            
arthurgorrie 1
SHAMROCK TEAM:

David Byrne
Estimator
 
John Esler, Les Nolte, John O’Hagan & Damien Goodwin
Site Supervisors
 
Nick Sandwell
Project Manager
 
Bevon Peddell
Project Coordinator



            

Arthur Gorrie Correctional Centre Expansion & Brisbane Reception Centre Expansion

CLIENT:  Bovis Lend Lease (Department of Corrective Services)
CLIENT REP:  Ron Melton / David Flood
CONTACT NO:   (07) 3271 1445
VALUE:  $7million
DURATION:  August 2006 – May 2008

grey-line

The objective of the correctional centre projects was to provide the Brisbane Reception Centre (BRC) and Arthur Gorrie Correctional Centre (AGCC) with increased cell accommodation and upgrades to the supporting services and infrastructure. While the BRC was non-operational during construction, AGCC was fully operational and required Shamrock Civil to operate within the strict site rules and protocols as set out by BLL and GEO (Arthur Gorrie Centre Management).
 
Works at the Arthur Gorrie Correctional Centre included:

  • Clearing and demolition of redundant services and pavements
  • Bulk excavation and reinstatement of uncontrolled fill to construct building pads for new cell blocks and administrative blocks.
  • Retaining walls and concrete walkways.
  • Stormwater and Sewer Drainage including tunnel boring under the external security fence, construction of a 100kL plastilined precast sewer storage facility and connection into existing sewer pump station
  • Roadworks for new asphalt surfaced visitor carpark and remedial works to the existing visitor carpark and security surveillance ring road.

Works at the Brisbane Reception Centre included:

  • Bulk Earthworks to construct building pads for new cell blocks, administration and visitor processing buildings.
  • Construction of 224 x 600mm diameter reinforced concrete bored piers for building foundations
  • Stormwater Drainage
  • Roadworks for new asphalt surfaced visitor carpark
  • Approximately 70,000m2 of turfed landscaping  

The works were completed and handed over on time without disruption to the operation of the correctional centre facilities.
 

arthur-gorrie 2
            
greyline-770
            
bbc 1
SHAMROCK TEAM:

Julia Nest
Estimator
 
Jim Steward
Site Supervisor
 
James Kennedy
Project Manager
 




            

Brisbane Boys College

CLIENT:  Watpac
CLIENT REP: John O’Kane
CONTACT NO: (07) 3251 6321
VALUE: $818K
DURATION: November 2007 – February 2008

grey-line
Brisbane Boys' College is an independent day and boarding school for boys, located in Toowong. Shamrock Civil were awarded the External Civil and Roadworks package for the redevelopment of the College.
The external civil and roadworks consisted of new internal roads, car park and bus set down area and modifications to Moggill road and Miskin Street entrances.
This work involved:
· The demolition of 3500m2 of existing road. Demolition of kerb, channel, crossovers, stormwater pipes and pits.
· Installation of 150m stormwater pipes and associated manhole and inlet structures.
· Concrete works which included approx 1200m of and channels(including subsoils), approx 380m2 of footpaths and two concrete roundabout infills..
· Two crossovers were also constructed, one at Moggill road one at Miskin Street
· Construction of 3800m2 of new asphalt pavement.
 
The new road was constructed parallel to the Toowong Creek, therefore it was essential maintain a high standard of silt management and environmental control to ensure the river remained free from any debris or contaminates.
Shamrock Civil worked closely with Watpac and the Brisbane boys college to ensure all works were carried out in a delicate and professional manner to ensure that the school operated successfully and uninterrupted throughout the full duration of the project.
 
All works were carried out to in accordance with Brisbane City Council Standards and completed on time and within budget.

bbc 2
            
greyline-770
            
narangba 1
SHAMROCK TEAM:

Julia Nest
Estimator
 
Luke Corcoran / John Esler
Site Supervisor
 
Sean Keane
Project Manager
 




            

Lot 2 Potassium Street, Narangba

CLIENT:  That Builder 
CLIENT REP: Maurice Granger 
CONTACT NO: 300 284 532
VALUE: $350K
DURATION: March - June 2008


grey-line
Shamrock Civil was contracted to carry out the earthworks, pavements and stormwater works at the Lot 2 Project at 100 Potassium Street Narangba for “That Builder”. The earthworks consisted of the stripping of the site, removal and reinstatement of unsuitable material, the cut to fill and importation of suitable fill. Shamrock also carried out the trimming of the building pad and extensive filling on the batters to allow for the construction of the new car park. Shamrock also undertook the construction of the pavements and kerbs for the new car park and access road. The contract also included the reshaping of the existing detention basin and the construction a new bio retention basin, headwalls and spillway. The works were completed on time to the satisfaction of the head contractor.
narangba 2
            
greyline-770
            
matisse 1
SHAMROCK TEAM:

David Byrne
Estimator
 
Derek Hennessy
Site Supervisor
 
Craig Jack
Project Manager
 




            

Matisse Tower

CLIENT:  FKP
CLIENT REP:  Daniel Deans
CONTACT NO: (07) 3334 8500
VALUE: $ 1.7m
DURATION: August 2007 – August 2008



grey-line
FKP engaged Shamrock Civil Engineering to do the bulk excavation and facilitate the Top Down construction of 3 basement levels for Matisse Towers in Mary St, Brisbane.
 
Combining the contaminated and constricted site with the Top Down construction and high level of co-ordination this job certainly possessed its fair share of potential issues.
 
The construction process involved preparing each level to have the slab poured. Once the slab was poured and cured SCE commenced the excavation and then under-mining of each level until the surface below was prepared for the concurrent slab. During this process SCE would remove the bulk of the material, scabble the walls, columns and roof where necessary, and demolish the lift pit over pour. SCE would then prepare any rebates or recesses and prepare the slab and then allow the concreters to pour the next slab.
 
As well as the restricted space and the potential safety issues apparent with a job like this, SCE also utilized specialized machinery to extract material up to 10m through the centre of the site in order to load Trucks on the top slab and remove the material.
matisse 2
            
greyline-770
            
citybeach 1
SHAMROCK TEAM:

David Byrne
Estimator
 
Darren Morris
Site Supervisor
 
Sean Keane
Project Manager
 




            

City Beach Warehouse

CLIENT:  Woollam Construction
CLIENT REP:  Ian Morris
CONTACT NO: (07) 3456 1600
VALUE: $ 500k     
DURATION: May 2008 – August 2008



grey-line
Shamrock Civil were contracted by Woollam Constructions to carry out the earthworks, pavements and stormwater works at the City Beach factory extension. The project consisted of the construction of the new stormwater lines, the associated structures, the installation of a Gross Pollutant Trap and the construction of a bio retention basin. Shamrock Civil also constructed 14m of 2700x1500 culverts to allow for the new entrance to the warehouse. These works were carried out whilst maintaining effective environmental and silt controls to protect the live creek. Shamrock also carried out the earthworks and the construction of a new 6100m2 building pad. These works were staged so as to allow the warehouse to remain fully operational during construction.  The construction of the new asphalt internal road was also part of Shamrock Civil’s package.
 
Shamrock Civil completed the project to the satisfaction of Woollam Constructions and on programme whilst allowing for the staging required to allow for the warehouse to remain open during construction.
 
citybeach 2
            
greyline-770
            
southbank 1
SHAMROCK TEAM:

James Kennedy
Estimator
 
Paddy O'Boyle
Site Supervisor
 
James Kennedy
Project Manager
 




            

Southbank Redevelopment

CLIENT:  John Holland
CLIENT REP:  Peter Furlong
CONTACT NO: (07) 3867 7000
VALUE: $ 560k     
DURATION: Aug 2008 - October 2008



grey-line
Southbank Institute of Technology lies in the heart of Brisbane’s Southbank district. It is Queensland's leading Institute of TAFE with more than 27,000 students enrolled. Since 2005, the Institute has been engaged in a $550m redevelopment project to create a world-class facility at its Southbank campus. Running through the heart of the TAFE campus is the Educational Pathway. Starting at Glenelg St. the pathway runs through Ernest St. to connect to Turbine St. on the opposite side of the campus. This connects Block E and Block C of the college together.

The package awarded to SCE was split into two stages. Stage 1 was the construction of a 700m2 visitor’s carpark located in the campus grounds, adjacent to Merivale St. Stage 2 comprised of the redevelopment of Ernest Street between Merivale St. and Colchester St.

Stage 1 works began at the end of August and comprised of:
·         The demolition and excavation of existing services in the carpark
·          Installation of 50m of Stormwater pipes, including construction of new pits and connections to existing.
·         Construction of 150m of Kerb, including subsoil’s to suit
·         Construction of 700m2 of Asphalt pavements, followed by linemarking and installation of signage.

Stage 2 works involved a full road closure. This had to be coordinated with John Holland and the Brisbane City Council to ensure there would be no clash with the River Fire festival. Stage 2 works started in early September after River Fire and ran concurrently with Stage 1. Works comprised of:
·         Location of existing services
·         Demolition of existing pavement, kerb and footpaths and preparation for new pavement
·         Installation of 80m of Stormwater pipes, including construction of new pits and connections to existing services.
·         Installation of 30m of ACO polycrete custom stainless steel grate and frame.
·         The Road was constructed from both asphalt and concrete and included ramps at either end.
·         Concrete works included placing colour concrete and placing an exposed concrete.
·         Thermoplastic linemarking and signage

For the duration of the project safety was the main priority for persons working on site and for the public and students passing by the site every day. The project was completed on budget and Ernest Street was reopened according to the program set by Brisbane City Council. 



southbank 2
            
greyline-770
            
taloona 1
SHAMROCK TEAM:

David Byrne
Estimator
 
Luke Corcoran
Site Supervisor
 
Liz Kirwan
Project Manager
 




            

Spring Gully Development - Taloona Gas Plant Access

CLIENT:  Origin Energy
CLIENT REP:  Adam Mann
CONTACT NO: (07) 3858 0702
VALUE: $ 3 million 
DURATION: June 2008 - December 2008



grey-line

The Spring Gully development project is located approximately 80km north of Roma in central Queensland. As part of the fifth stage of the development of the Spring Gully Gas Field, it was necessary to construct a new road to the natural gas compressor plant on the Taloona property.

Shamrock Civil were the contractors appointed to supply the materials, labour and plant for the construction of over 6km of primary sealed road linking the Taloona Gas Plant to the existing public road (Wybara Road).

These works comprised of:

  • Strip and grade 20m wide track for the proposed 6km length of road.
  • Demolition and removal of old existing creek crossings, motor grids and fencing.
  • Earthworks and subgrade preparation for the construction of the 6km road formation. (50,000m3 cut to fill & 15,500m3 cut to spoil)
  • Bituminous surfacing (45,000m2)
  • Construction of culverts (both box and pipe – including R.C. footings, slabs, walls, wing-walls, head-walls and aprons), flood ways and scour protection.
  • Embankment and slope stabilization including the supply and installation of shotcrete, rock pitching and grouted rock pitching, rock check-dams (slopes / cut off drains / side drains)
  • Supply and installation of all road fixtures, flood level markers, regulatory signage, guardrails and terminals.
  • Respread, seeding and fertilizing of topsoil to drains, gullies, embankments and batters (20,000m2)
  • Maintenance and upkeep of the temporary Gas Plant access road during the works to maintain a safe traffic flow.
taloona 2
            
greyline-770
            
s2k 1
SHAMROCK TEAM:

David Byrne
Estimator
 
Alex Geuna, Jim Steward, John Esler, Eamonn Turner, Sean Lucas
Site Supervisors
 
Liz Kirwan & David Carney
Project Managers
 





            

Salisbury to Kuraby Rail Upgrade

CLIENT:  S2K Alliance
CLIENT REP:  Eugene Newman
CONTACT NO: (07) 3457 4404
VALUE: $ 8.2 million
DURATION: December 2006 - January 2008



grey-line

The Salisbury to Kuraby Rail Upgrade was delivered by the S2K Alliance, a partnership between QR Limited and Abigroup Contractors. The works consist of 9.5km of new track and the upgrade of 7 stations.
 
Shamrock Civil were awarded the Carparks, Roadworks and Stormwater Drainage contract for Altandi, Coopers Plains, Fruitgrove, Kuraby, and Runcorn Station.
 
The Contract comprised of the following major activities:
 
Demolition & removal of existing carparks, roads, stormwater and services.

  • Demolition & removal of existing carparks, roads, stormwater and services.
  • 4,700m3 of bulk excavation.
  • 4,500m3 of bulk fill.
  • 16,500m3 of detailed excavation for roadworks.
  • Placement of over 26,000m2 of new pavement, consisting of 16,000m3 of roadbase and over 3000 tonne of asphalt.
  • Construction of 8,200m2 of coloured concrete paving, feature paving, concrete footpath & concrete driveway &  kerb ramps.
  • Placement of 5,300m of kerb and channel.
  • Construction of 2 asphalt roundabouts and numerous concrete traffic islands. 
  • Laying of 1,300m of reinforced concrete stormwater pipes and 75 stormwater structures including Gross Pollutant Traps, manholes, field inlets & gully pits.
  • 3,200m of subsoil drains
  • Placement of over 3,500m of underground communication & electrical conduits & 170 associated pits.
  • Construction of over 100 street light pole footings.
  • Road signage, linemarking, speed bumps, traffic bollards & fencing.
  • Topsoiling and soft landscaping.  


A large proportion of the road works were carried out on roads which carry high traffic volumes. Works to the Beenleigh Road and Henley Street required a large amount of traffic management and staging in order to construct new pavements, concrete islands, a roundabout and traffic signal works with out disrupting the flow of traffic.
 
As all stations remained operational for the duration of the project the works were programmed to ensure no disruption was caused to the public or railway.
 
Shamrock Civil completed the project on time and to the satisfaction of the S2K Alliance.
 

s2k 2
            
greyline-770
            
murrumba 1
SHAMROCK TEAM:

Julia Nest
Estimator
 
Bertie Jones
Site Supervisor
 
David Carney
Project Manager
 




            

Murrumba Downs Waste Water Treatment Plant

CLIENT:  John Holland
CLIENT REP:  Jeff Andrew
CONTACT NO: (07) 3897 7712
VALUE: $ 400 k
DURATION: July 2008 - August 2008



grey-line
The contract involved a bulk excavation adjacent to an existing treatment facility in order to accommodate the upgrade and reconstruction of the new facility. All materials excavated from site were acid sulphate materials and had to be lime treated prior to being removed from site.
 
A filling area was prepared adjacent to the excavation site and all materials were tested onsite and treated with a lime dosage according to their acidity.
 
Once the excavation and filling/treatment process was complete and all material had passed a retesting process, it was removed from site and utilized as fill material.
 
Working in and around an existing facility required constant consultation and communication with the client in order to facilitate the bulk excavation process and the plant production.
murrumba 2
            
greyline-770

 
            
Workshop and offices 309 Progress Road, Wacol, Brisbane Qld 4076 • Phone (07) 3879 4300  Fax (07) 3879 4844