CLIENT: Westfield Design and Construction
VALUE: $975,000
DURATION: March 2004 - October 2004
This contract included earthworks, stormwater and electrical conduit installation. The major component of our works is including construction of approximately 15,000m2 of flexible pavement for a new carpark at Westfield's Garden City.
Pavements included heavy duty access roads, intersections and light duty carpark areas. The contract also included linemarking and road furniture.
Prior to completion we undertook the hard landscaping to the perimeter of the site.
All works were completed in accordance with Brisbane City Council standards and MPN specifications.
Our contract also included works to the main entry / drop off zone, these works were programmed to cause minimum disruption to the public.
|
|